September 9, 202625
Short answer: A complete purlin production line needs seven equipment groups in one sequence: hydraulic decoiler → leveler → hydraulic pre-punch → roll forming main unit → cut system → PLC control cabinet + HMI → run-out table. A mid-size CZ line typically processes 1–3.2 mm galvanized coil into C/Z purlins with webs of 80–300 mm, at 12–32 m/min depending on configuration, with ±1–2 mm length accuracy under PLC control. Budget in four parts: forming main unit, coil handling, punching/cutting hydraulics, and controls/auxiliaries — and always check what each quote includes before comparing.
This guide lists every module, explains capacity planning, gives a factory layout sketch, and compares starter vs automated budget tiers.
Optional but valuable: inkjet marking (prints size/batch per piece) and automatic stackers/strappers at the high-volume end.
Published process data (ZTRFM) for a CZ auto-changeover line:
| Module | Example specification |
|---|---|
| Decoiler | Dual-head hydraulic, 6 t/head (12 t), width ≤600 mm, ID 450–550 mm, OD 1730 mm, brake, electric rotation |
| Forming | 20 stands; rollers Cr12 HRC 58–60; shafts 40Cr Φ90/75; chain drive; optional emboss rolls |
| Punch/cut | Hydraulic pre-punch, 3 stations; cut + punch power 15 kW; oil tank 300 L |
| Drive | Servo host 42 kW; high ~32 m/min, normal 12–18 m/min; 380 V / 50 Hz / 3-phase |
| Gauge | 1–3.2 mm Q235/Q355 (HR or GI); inkjet marking; 6 m run-out table; Xinje PLC; ZH/EN UI |
| Changeover | Auto C↔Z recipe in HMI, ~90–120 s |
Estimate output with this sequence:
Choose decoiler class (3–5 t vs 6 t/head dual) by your largest coil and how often you tolerate changeover stops.
Minimum line footprint and surroundings to plan:
Ask the supplier for the exact floor plan (footprint × power × weight) before civil work.
| Tier | What you get | Typical position |
|---|---|---|
| Starter single-profile | C-only or fixed-size line, manual change, stop-cut, basic decoiler | Lowest capital; fixed product |
| CZ convertible | Manual C/Z changeover, pre-punch, hydraulic cut, standard PLC | Balanced for mixed markets |
| Auto-changeover CZ | Recipe C↔Z (~90–120 s), servo host, dual-head decoiler, marking | High-mix shops; higher capital |
| CUZ / fully automated | C+U+Z auto width, stacker/strapper, remote support | Maximum flexibility and throughput |
Price moves most with: changeover type (manual → auto), cut system (stop-cut → servo tracking), punching stations, decoiler capacity, and control/automation level. Always request a spec-sheet quote — the same "purlin machine" name can mean very different line scopes.
ZTRFM (zt-rfm.com) is a roll forming sourcing center operated by Zhongtuo Roll Forming (Hebei) Co., Ltd. Purlin standards commonly referenced include AISI S240 / ASTM A1003 (US) and GB/T 6723 (China) for cold-formed open sections.
What equipment is needed for a purlin production line? Seven groups in sequence: hydraulic decoiler, leveler, hydraulic pre-punch station, roll forming main unit, cut system, PLC control cabinet + HMI, and a run-out table. Optional: inkjet marking, stackers and strappers.
How much space does a purlin line need? Typically a straight bay of roughly 20–30 m including decoiler and a 6 m run-out table, plus coil storage and finished-goods areas; confirm the exact footprint with the supplier.
How fast is a purlin production line? Typical normal forming speeds 12–18 m/min for CZ lines with high-speed modes around 32 m/min; single-profile lighter lines can run faster, thicker gauge slower.
What is a pre-punch station for? It punches web holes before forming while the web is flat, keeping hole positions accurate — standard on purlin lines (commonly 2–3 hydraulic stations).
What is the difference between stop-cut and servo tracking cut? Stop-cut pauses the line to cut; servo tracking cut cuts on the move for higher throughput. Length accuracy is typically ±1–2 mm under PLC control.
How much does a purlin production line cost? Prices vary widely with changeover type, cut system, decoiler and automation. Compare spec-sheet quotes (gauge, width, stations, power, decoiler, included line scope) rather than machine name or price alone.
Article by ZTRFM — Roll Forming Sourcing Center. Specs cited from published ZTRFM product and process documentation; verify final configuration with your supplier before purchase.